Key milestones of a turnaround project

ShutdownMSMilestones
Shutdown Strategy1Kick Off Meeting: Appoint a Shutdown Coordinator
2Present & finalize the Shutdown Strategy Data Sheet

Front End Loading
3First shutdown meeting. Contractors and activity owners (maintenance and project engineers) present their scope and review the lessons learnt from the last shutdown.
4Internal scope review meeting held.
5Procure Long lead materials
Detailed Planning6Capture and incorporate any unavoidable late work
7Work Pack preparation
8Freeze Scope of Work
9Conduct Scope Optimisation Exercise – Lean thinking workshops
Pre Shutdown Work10Reconcile Materials
11Issue signed approved shutdown handbook.
12Plant Decommissioning / maintenance / Recommissioning / Clearance for operations
Post Shutdown work13Review actions taken. Transfer finding to shutdown lessons learnt spreadsheet.

There are several other important topics such as logistics, HSE and contracting/ procurement, which are just as vital to the successful execution of a turnaround as the others.

It is also a good practice to conduct a standard turnaround review typically by a third party . Such reviews can provide valuable insights on the progress of the above-mentioned key milestones. It helps assess the site’s preparedness and understand the potential risks that could negatively impact the planned cost and duration of the turnaround. A consistent and transparent approach coupled with a motivated team is what makes preparation successful on the front end.

This will ultimately lay the foundation for a successful yet safe execution as well.